Philnpt wrote:The bottom figure would be AOD which means above ordinance datum, in other words 8.5m above sea level
Cheers Phil!
---------------------------------------------------------------------------------------------------------------------------
Looking at the schedule of works...
We will see a lot of activity on site from next month with DCWW drainage works to Saunders Road. Then the main contract commencement in december this year, when piling will commence until march next year.
Then Pile caps and ground beams January 2020 - July 2020
Superstructure Frame Completion for Interchange, November 2020
Office, February 2021
PRS Tower October 2021
Car Park, January 2022
overall completion date is august 2022
So there's going to be plenty to keep an eye on if all goes to plan in the not too distant! but from the above it looks like we won't see a development rising above the hoardings until about a year from now. That said if actual construction starts from july(ish) next year then can we assume that 3 or 4 or 5? tower cranes will be erected by then?