Churchill Way Canal Feeder

PostPosted: Thu Jan 06, 2022 5:38 pm
by Amoore
Image

Work is due to start on this in the next week or so. In order to begin the works the Capitol Centre's steel canopy needs to be removed so I understand this will be the first activity taking place before the hoarding goes up.

Re: Churchill Way Canal Feeder

PostPosted: Thu Jan 06, 2022 11:49 pm
by Simon_SW17
Good to see it starting, if a little later than summer 2021 as promised. I did wonder why there were grass mounds and picnic benches all over the area when I came home in July.

Re: Churchill Way Canal Feeder

PostPosted: Fri Jan 07, 2022 5:22 pm
by AWarmerBeer
Hope we see more activity on the Canal Quarter masterplan this year. I don't think there's been anything since the initial application went in last May?

Re: Churchill Way Canal Feeder

PostPosted: Sat Jan 08, 2022 11:26 am
by Ash
I know you have to start somewhere but I think this short stretch of open water is going to look a bit odd and out of place. Hopefully it won't be too long before it's extended.

Re: Churchill Way Canal Feeder

PostPosted: Sat Jan 08, 2022 6:43 pm
by DJKiran
Can't wait for this to get going!

Re: Churchill Way Canal Feeder

PostPosted: Mon Jan 10, 2022 1:33 pm
by Amoore
Ash wrote:I know you have to start somewhere but I think this short stretch of open water is going to look a bit odd and out of place. Hopefully it won't be too long before it's extended.


I think it's best to think of it more as an elaborate water feature rather than a stretch of water. There's going to be a waterfall at the Queen Street end so it will be constantly flowing and won't be that deep according to the plans.

Some piles of heras fencing have appeared on the street today.

Re: Churchill Way Canal Feeder

PostPosted: Fri Jan 28, 2022 4:06 pm
by Amoore
https://www.walesonline.co.uk/news/loca ... r-22907886

Some new images showing the bandstand area:

Image

Image

Re: Churchill Way Canal Feeder

PostPosted: Thu Feb 17, 2022 4:06 pm
by CardiffRocks
Long time lurker finally got round to posting!!!

Looks like works are starting up on site. Saw a few of the contractors marking out services this morning.

Also saw this in the news..

https://www.walesonline.co.uk/whats-on/ ... es_cardiff

Looks like this will be a good location, and could really revitalize this corner of the city with the Canal Quarter development. I've been to the one in Sheffield and was impressed.

Re: Churchill Way Canal Feeder

PostPosted: Fri Feb 18, 2022 12:46 am
by paul cardiffwalesmap
To true 'Cardiff Rocks' the Capitol centre is fighting back with various new ventures planned! This end of town is going to balance things out a bit when all proposed, completed. Oh and welcome! glad you could lurk no more and joined the forum! it's been pretty quiet of late but we're still here! and you are on board just as hopefully we start getting a bit busier!! :)

Re: Churchill Way Canal Feeder

PostPosted: Wed Feb 23, 2022 6:28 pm
by Amoore
The road is now closed and the hoarding is going up, with very little room left for Pulse's outside area which is usually very busy at the weekend. Obviously Pulse stands to gain a lot in the long run but I can see it being a right pain in the wotsit for the next 6 months or so.